LCD Orynbor Towers project manager Aidan
Narymbaev shared how to build 5 floors a month without loss of quality.
What gift for the New Year can be called the
best? Of course, keys to a new apartment! According to the plan, 270 clients
were to receive their keys in May of the following year, but the project team
did everything to ensure that this event took place 5 months earlier.
“Lean manufacturing, optimization and
unification of business processes allowed us to achieve this result. For
example, we used powerful QTZ-80 cranes capable of operating at a wind speed of
15 meters per second.” While other construction projects stopped due to the
storm warning, our work was well under way. We used a higher class and brand of
concrete. This can be a more expensive option, but we succeeded in terms of strength,”
says the project manager.
Much of what we have seen is already the
standard for the company: technology to increase sound insulation "wall in
the wall", protection from children falling out, panoramic windows,
blow-in valves, and the game room inside the complex that is so far the Orynbor
Towers feature. Of course, there are wonderful children's and sports grounds on
the street, but if it’s cold or raining, you can tear yourself away from
gadgets and have a real chat with your neighbors.
All this was appreciated by happy new settlers.
Saltanat:
"BI Group has proven itself as a company
that builds quality housing on the market. This house reminded me of Manhattan,
such an unusual design. Plus my job is nearby. I think sons Arslanbek and
Asylbek will like it here."
Nesibeli:
"We rented housing in “Dostar” RC, our friends
live in “Arman Kala”, so the choice of the company did not even arise. And this
house was chosen because there is a school nearby. The outgoing year is full of
bright events for us such as housing purchase and keys receiving, Nurali turned
one, Iskander went to the kindergarten, and we also have two other children,
Nurbakhyt and Alina."
Many customers will have to take care of
renovations in the New Year, but 32 families who ordered finishing should only
bring their things and live in their new apartments. By the way, already in
July-August, the second phase of this interesting project is scheduled to be
delivered.